Registration of De Facto Adoption Applications to register a de facto adoption of a Muslim and non-Muslim child under Act 253 shall be processed and completed within the following time frames from the date of receipt of the complete applications at any NRD counter: |
|
|
|
| |
a. For applications received at counter: |
|
|
|
| |
i. For data that has been updated in the system |
5 working days |
5 working days |
5 working days |
| |
ii. For data that has not been updated in the system |
7 working days |
7 working days |
7 working days |
| |
b. For applications received by post: |
|
|
|
| |
i. For data that has been updated in the system |
5 working days |
5 working days |
5 working days |
| |
ii. For data that has not been updated in the system |
7 working days |
15 working days |
7 working days |
| 2 |
Extract of De Facto Adoption Certificate Applications to obtain an extract of a de facto adoption certificate shall be processed and completed within the following time frames from the date of receipt of the complete applications at any NRD counter: |
|
|
|
| |
a. For applications received at the counter: |
|
|
|
| |
i. For data that has been updated in the system |
20 minutes |
20 minutes |
20 minutes |
| |
ii. For data that has not been updated in the system |
5 working days |
5 working days |
5 working days |
| |
b. For applications received by post: |
|
|
|
| |
i. For data that has been updated in the system |
7 working days |
7 working days |
7 working days |
| |
ii. For data that has not been updated in the system |
10 working days |
10 working days |
10 working days |
| 3 |
Amendment of Details into the De Facto Adoption Certificate Applications to amend the details of a de facto adoption certificate shall be processed and completed within the following time frames from the date of receipt of the complete applications at NRD counter: |
|
|
|
| |
a. For applications received at the counter: |
|
|
|
| |
i. For data that has been updated in the system |
5 working days |
15 working days |
15 working days |
| |
ii. For data that has not been updated in the system |
7 working days |
15 working days |
15 working days |
| |
b. For applications received by post: |
|
|
|
| |
i. For data that has been updated in the system |
5 working days |
7 working days |
7 working days |
| |
ii. For data that has not been updated in the system |
7 working days |
15 working days |
15 working days |
| 4 |
Registration of Adoption by Court Order Applications to register an adoption by court order under Act 257 for non-Muslim adopted child and adoptive parents shall be received, processed and completed by the Birth, Death and Adoption Division of the NRD Headquarters in Putrajaya.
|
7 working days
|
-
|
-
|
| 5 |
Change/Replacement/Amendment of Birth Certificate of Adopted Child Applications to change/replace/amend the birth certificate of an adopted child under Act 257 shall be received, processed and completed by the Birth, Death and Adoption Division of the NRD Headquarters in Putrajaya within the following time frames from the time/date of receipt of the complete applications: |
|
|
|
| |
a. For applications received at counter: |
|
|
|
| |
i. For data that has been updated in the system |
20 minutes |
- |
- |
| |
ii. For data that has not been updated in the system |
5 working days |
- |
- |
| |
b. For applications received by post: |
|
|
|
| |
i. For data that has been updated in the system |
5 working days |
- |
- |
| |
ii. For data that has not been updated in the system |
10 working days |
- |
- |
| 6 |
Amended Court Order on Adoption The adoption order by the Registrar through an amended court order shall be processed and completed by the Birth, Death and Adoption Division at the NRD Headquarters in Putrajaya. |
10 working days
|
-
|
-
|